Biomass Pellet Project under the National Bioenergy Programme by the Government of India. Here are some key points:
Programme Approval:
The National Bioenergy Programme is approved for the period from April 1, 2021, to March 31, 2026, with a budget outlay of ₹858 crore for Phase-I.
It includes three sub-schemes: Waste to Energy Programme, Biomass Programme, and Biogas Programme.
Budget Allocation:
Waste to Energy Programme: ₹600 crore
Biomass Programme: ₹158 crore
Biogas Programme: ₹100 crore
Exclusions:
Bagasse-based Biomass Cogeneration projects are not supported under the Biomass programme.
Eligibility and Assistance:
The programme supports the setting up of Biomass Briquette/Pellet manufacturing plants and Biomass (non-bagasse) based cogeneration projects in industries.
Central Financial Assistance (CFA) is provided as follows:
₹9 lakh per metric ton/hour (MTPH) manufacturing capacity for Briquette/Pellet manufacturing plants, with a maximum CFA of ₹45 lakh per plant.
₹40 lakh per MW for Biomass (non-bagasse) cogeneration projects, with a maximum CFA of ₹5 crore per project.
Service Charges:
Implementing agencies receive a service charge of 1% of the total CFA for processing applications.
Performance inspection agencies receive service charges for monitoring and verification:
₹25,000 per MTPH (maximum ₹1 lakh per project) for Briquette/Pellet plants.
₹1 lakh/MW (maximum ₹5 lakh per project) for Biomass cogeneration projects.
Conditions:
Projects must use biomass like crop residues, wood from energy plantations, industrial wood waste, agro-based industrial residues, and forest residues.
Municipal solid waste, black liquor, slop, press mud, and other processed industrial waste are not eligible.
Minimum plant sizes are 1 MTPH for Briquette/Pellet plants and 0.5 MW for Biomass cogeneration plants.
Proposals must be submitted before commissioning the projects.
Procedure for Availing CFA:
Proposals should be submitted through the BioURJA Portal.
“In-principle” approval is required for projects, with specific conditions for projects with and without loans.
The commissioning of the plant should occur within specified time frames after receiving “in-principle” approval.
Performance inspection must be conducted within 18 months of commissioning.
Implementing Agency:
The Indian Renewable Energy Development Agency Limited (IREDA) is the implementing agency.
Guidelines and Appendices:
Detailed guidelines for the implementation of the Biomass Programme are provided in the document.
Here are the detailed conditions for the setup of a biomass pellet manufacturing plant according to the document:
Terms and Conditions
Eligible Biomass Types:
Crop residues such as paddy straw, wheat straw, mustard stalks, and cotton stalks.
Wood from energy plantations (e.g., prosopis juliflora).
Weeds, palm leaves, coconut shells, and husk.
Wood waste from industrial operations (e.g., sawdust, off cuts, bark).
Forest residues such as pine needles, branches, and stems of trees.
Eligible Projects:
Only projects for setting up briquette/pellet manufacturing plants and biomass (non-bagasse) cogeneration projects are eligible.
Bagasse-based cogeneration projects are not eligible.
Projects using municipal solid waste, black liquor, slop, press mud, and other processed industrial waste are not considered.
Eligibility Criteria:
Companies registered under the Companies Act, Partnership Firms, Proprietorship Firms, Cooperatives, Public Sector Companies, and Government-owned Firms are eligible for financial support.
Minimum project/plant size requirement:
Briquette/Pellet Manufacturing Plant: 1 MTPH (metric tons per hour).
Biomass (non-bagasse) Cogeneration Power Plant: 0.5 MW.
Financial Assistance and Application:
Central Financial Assistance (CFA) will be provided after successful commissioning and performance inspection of the plant.
Proposals for availing CFA should be submitted before the commissioning of the projects, except for specific cases mentioned in the document.
CFA should not be claimed from any other Ministry or department of the Central Government for the proposed plant.
Only projects installing new machinery (e.g., briquette/pellet making machinery, boiler, turbine) are eligible for CFA.
Safety and Statutory Requirements:
Measures should be taken to ensure the safety of stored biomass.
Necessary statutory clearances must be obtained from appropriate Central/State Government bodies before establishing or commissioning the plant.
The plant should share generation data with the Ministry of New and Renewable Energy (MNRE) or any designated agency through the installation of SCADA/remote monitoring system.
Biomass (non-bagasse) cogeneration plants should not utilize any fossil fuel.
Other Conditions:
The project should not be dislocated or dismantled without prior information to the Ministry.
The Ministry reserves the right to access project-related data for publishing success stories, case studies, technical papers, and for third-party inspection and evaluation of the project’s operation and performance aspects.
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behavior or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional
Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes.The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.