  1. Introduction:
    • NTPC Limited, a Maharatna company, is India’s largest power generation company, aiming to reduce its carbon footprint and achieve net-zero goals.
    • Decarbonisation of coal power assets through biomass utilization is a key strategy.
    • NTPC aims to enhance biomass co-firing in its coal-fired power plants.
  2. Objective:
    • NTPC seeks to identify interested parties for the supply of torrefied pellets.
    • Torrefied biomass pellets offer higher energy efficiency and reduce transportation costs.
  3. Eligibility:
    • Developers: Business entities collaborating with torrefaction technology partners.
    • Aggregators: Business entities with experience in biomass aggregation, in collaboration with torrefied pellet manufacturers.
    • Consortiums: Biomass pellet manufacturers forming a consortium.
    • Individual Companies/Firms: Firms with tie-ups with biomass collectors and torrefaction technology manufacturers or torrefied pellet manufacturers.
  4. Submission Requirements:
    • Documents: Covering letter, business-related information, technical details of torrefied pellet plants, and notarized Power of Attorney.
    • Submission: Softcopy via email and hard copy in person or by registered/speed post.
  5. Evaluation:
    • Evaluation based on the information provided, including visits to manufacturing units, technology assessment, and financial capability analysis.
    • Vendors must demonstrate the operational capability of their torrefaction reactor.
  6. Agreement and Capacity:
    • Shortlisted vendors may set up torrefied pellet plants near NTPC stations.
    • NTPC may enter into agreements for the procurement of torrefied biomass pellets.
    • Plant capacities starting from 20 TPD for small-scale viability testing, with larger reactors starting at 100 TPD for larger consumers.
  7. Important Dates:
    • Last date for queries: 10 days from EOI publication.
    • Last date for submission: 20 days from EOI publication.
  8. Contact Information:
    • Submissions and queries should be directed to Sh. G.S. Gawra and Sh. Ashwini Kumar Verma at NTPC.

Contact Details:

  • G.S. Gawra:
    • Email: [email protected]
    • Address: EOC Complex, NTPC limited, Sector 24, NOIDA – 201301
  • Ashwini Kumar Verma: